Morgan Est Rail: Kirkaldy Railway Station
Client: Morgan Est
Project: Kirkaldy Railway Station
Value: £700k
Start: 2007
Completion: 2008
Scope:
This contract was run by Network Rail and sponsored by the Scottish executive.
Kirkaldy was one of a number of stations having its disabled facilities upgraded.
The work consists of excavating the platforms and installing two lift shafts also a pedestrian ramp for access to the subway and also platform number 1.
In the execution of these works there is a requirement for sheet piling, re-enforced concrete works, block work and re-instatement of platforms, steel handrails as well as sheeting to roof and walls.
Works Also Include:
- Installation of diverse drainage system
- Underpinning of platform wall on platform1
- Installation of electrical duct work from power room to proposed lift shaft
- Excavate lift shaft base and install formwork for lift
- Pour mass concrete for lift shaft
- Construct block work for plant room
- Install roof steel work and sheet with box profile sheets
- Install ramps to platform 1
- Finish external cladding in Fyfe stone or equivalent
The same type of construction was carried out on platform 2.